Construction Updates

1st November 2023 Report

Tower A -
    1). External sit-out railing - completed all floors
    2). Tiles work - flooring completed all floor
    3). Door's - completed till 20th floors
    4). Windows - completed till 20th floor

Tower B -
    1). External sit-out railing - completed all floor
    2). Tiles work - flooring completed all floor
    3). Door's - completed till 20th floors
    4). Window's - completed till 27th floor

Tower C -
    1). External sit-out railing - completed all floor
    2). Tiles work - flooring completed all floor
    3). Door's - completed till 20th floors
    4). Windows - completed 20th floor

Tower D -
    1). External sit-out railing - completed all floor
    2). Tiles work - flooring completed all floor
    3). Door's - completed till 20th floors
    4). Window's - completed 11th to 20th floor

Clubhouse - Internal work in progress.
   

1st November 2023 Report

1st July 2023 Report

A- BLOCK -
    1). External sit out railing - completed 22nd floor.
    2). Tiles work - completed 26th floor.
    3). Fire fighting - completed all floors.

B- BLOCK -
    1). External sit out railing - completed all floors.
    2). Tiles work - completed all floors.
    3). Fire fighting - completed all floors.

C- BLOCK -
    1). External sit out railing - completed all floors.
    2). Tiles work - completed all floors.
    3). Fire fighting - completed all floors.

D- BLOCK -
    1). External sit out railing - completed all floors.
    2). Tiles work - completed all floor.
    3). Fire fighting - completed all floors.

Clubhouse - Internal work in progress.
   

1st July 2023 Report

1st June 2023 Report

A- BLOCK -
    1). External sit-out railing - completed 21st floor.
    2). Tiles work - completed 25th floor.
    3). Fire fighting - completed 25th floor.

B- BLOCK -
    1). External sit-out railing - completed all floors.
    2). Tiles work - completed all floors.
    3). Fire fighting - completed all floors.

C- BLOCK -
    1). External sit-out railing - completed all floors.
    2). Tiles work - completed all floors.
    3). Fire fighting - completed all floors.

D- BLOCK -
    1). External sit-out railing - completed all floors.
    2). Tiles work - completed 26th floor.
    3). Fire fighting - completed all floors.

Clubhouse - Internal work in progress.
   

1st June 2023 Report

1st May 2023 Report

A- BLOCK -
    1). External sit out railing - completed 21st floor.
    2). Tiles work - completed 23rd floor.
    3). Fire fighting - completed 23rd floor.

B- BLOCK -
    1). External sit out railing - completed 27th floor.
    2). Tiles work - completed 23rd floor.
    3). Fire fighting - completed all floors.

C- BLOCK -
    1). External sit out railing - completed 24th floor.
    2). Tiles work - completed 26th floor.
    3). Fire fighting - completed all floors.

D- BLOCK -
    1). External sit out railing - completed 16th floor.
    2). Tiles work - completed 25th floor.
    3). Fire fighting - completed 26th floor.

Clubhouse - Internal work in progress.
   

1st May 2023 Report

1st April 2023 Report

A- BLOCK -
    1). External sit out railing - completed 17th floor.
    2). Tiles work - completed 19th floor.
    3). Fire fighting - completed 23rd floor.

B- BLOCK -
    1). External sit out railing - completed 27th floor.
    2). Tiles work - completed 20th floor.
    3). Fire fighting - completed all floors.

C- BLOCK -
    1). External sit out railing - completed 20th floor.
    2). Tiles work - completed 24th floor.
    3). Fire fighting - completed all floors.

D- BLOCK -
    1). External sit out railing - completed 14th floor.
    2). Tiles work - completed 23rd floor.
    3). Fire fighting - completed 26th floor.

Clubhouse - Internal work in progress.
   

1st April 2023 Report

1st March 2023 Report

A- BLOCK -
    1). External sit out railing - completed 17th floor.
    2). Tiles work - completed 18th floor.
    3). Fire fighting - completed 21st floor.

B- BLOCK -
    1). External sit out railing - completed 27th floor.
    2). Tiles work - completed 19th floor.
    3). Fire fighting - completed all floors.

C- BLOCK -
    1). External sit out railing - completed 20th floor.
    2). Tiles work - completed 22nd floor.
    3). Fire fighting - completed all floors.

D- BLOCK -
    1). External sit out railing - completed 14th floor.
    2). Tiles work - completed 20th floor.
    3). Fire fighting - completed 26th floor.

Clubhouse - Internal work in progress.
   

1st March 2023 Report

1st February 2023 Report

A- BLOCK -
    1). External sit out railing - completed 16th floor.
    2). Tiles work - completed 14th floor.
    3). Fire fighting - completed 21st floor.

B- BLOCK -
    1). External sit out railing - completed 22nd floor.
    2). Tiles work - completed 16th floor.
    3). Fire fighting - completed all floors.

C- BLOCK -
    1). External sit out railing - completed 18th floor.
    2). Tiles work - completed 18th floor.
    3). Fire fighting - completed all floors.

D- BLOCK -
    1). External sit out railing - completed 14th floor.
    2). Tiles work - completed 16th floor.
    3). Fire fighting - completed 26th floor.

Clubhouse - Internal work in progress.
   

1st February 2023 Report

1st January 2023 Report

A- BLOCK -
    1). External sit out railing - completed 16th floor.
    2). Tiles work - completed 10th floor.
    3). Fire fighting - completed 20th floor.

B- BLOCK -
    1). External sit out railing - completed 21st floor.
    2). Tiles work - completed 14th floor.
    3). Fire fighting - completed 26th floor.

C- BLOCK -
    1). External sit out railing - completed 18th floor.
    2). Tiles work - completed 16th floor.
    3). Fire fighting - completed 23rd floor.

D- BLOCK -
    1). External sit out railing - completed 14th floor.
    2). Tiles work - completed 12th floor.
    3). Fire fighting - completed 26th floor.

Clubhouse - Internal work in progress.

1st January 2023 Report

1st December 2022 Report

A- BLOCK - 26th Floor work in progress.
B- BLOCK - G+27th Floors completed.
C- BLOCK - G+27th Floors completed.
D- BLOCK - G+27th Floors completed.
Clubhouse - G+5 Floors completed.

1st December 2022 Report

1st November 2022 Report

A- BLOCK - 25th Floor Pour 1- shuttering work in progress, Pour -2 Reinforcement in progress.
B- BLOCK - G+27th Floors completed.
C- BLOCK - G+27th Floors completed.
D- BLOCK - 27th Floors Pour-1 Reinforcement in progress.
Clubhouse - G+5 Floors completed.

1st November 2022 Report

1st October 2022 Report

A- BLOCK - 22nd Floor Pour- 1 completed, Pour-2 Reinforcement in progress.
B- BLOCK - G+27th Floors completed.
C- BLOCK - G+27th Floors completed.
D- BLOCK - 25th Floor Pour- 1 shuttering in progress.
Clubhouse - G+5 Floors completed.

1st October 2022 Report

1st September 2022 Report

A- BLOCK - 20th Floor Pour- 1 completed, Pour-2 slab Reinforcement in progress.
B- BLOCK - 27th Floor wall shuttering in progress.
C- BLOCK - G+27th Floors completed.
D- BLOCK - 22nd Floor Pour- 1 completed, Pour- 2 shuttering in progress.
Clubhouse - 5th Floor slab Reinforcement in progress.

1st September 2022 Report

1st August 2022 Report

A- BLOCK - 17th Floor Pour- 1 in progress.
B- BLOCK - 25th Floor shuttering in progress.
C- BLOCK - 26th Floor pour- 1 completed, Pour- 2 shuttering in progress.
D- BLOCK - 19th Floor Pour-1 shuttering in progress, Pour- 2 Reinforcement in progress.
Clubhouse - 4th Floor completed.

1st August 2022 Report

1st July 2022 Report

A- BLOCK - 15th Floor completed, 16th Floor Reinforcement in progress.
B- BLOCK - 23rd Floor Pour - 1 Completed, Pour - 2 shuttering in progress.
C- BLOCK - 24th Floor completed.
D- BLOCK - 17th Floor completed.
Clubhouse - 4th Floor roof shuttering in progress.

1st July 2022 Report

1st June 2022 Report

A- BLOCK - 14th Floor Concrete work completed.
B- BLOCK - 22nd Floor shuttering work in Progress.
C- BLOCK - 23rd Floor Pour-1 completed, Pour-2 in concrete in progress.
D- BLOCK - 16th Floor Shuttering work in progress.
Clubhouse - 4th Floor Shuttering work in progress.

1st May 2022 Report

1st May 2022 Report

A- Block - 12th Floor shuttering work in progress.
B- Block - 19th Floor shuttering work in progress.
C- Block - 20th shuttering work in progress.
D- Block - 12th completed, 13th Floor pour-1 ready for concrete.
Clubhouse - 02nd Floor shuttering in progress.

1st May 2022 Report

1st April 2022 Report

A- Block - 10th Floor roof shuttering in progress.
B- Block - 17th Floor roof shuttering in progress.
C- Block - 19th Floor Pour -1 roof shuttering completed, Pour -2 shuttering in progress.
D- Block - 12th Floor roof shuttering in progress.
Clubhouse - 01st Floor completed.

1st April 2022 Report

1st March 2022 Report

A- Block - 07th floor Pour - 1 completed, Pour - 2 shuttering in progress.
B- Block - 14th floor Pour -1 roof in progress, Pour - 2 shuttering in progress.
C- Block - 16th floor Pour -1 roof concrete in progress, Pour -2 shuttering in progress.
D- Block - 09th Floor Pour- 1 completed, Pour- 2 ready for concrete.
Clubhouse - Second floor level slab shuttering in progress.

1st March 2022 Report

1st February 2022 Report

A- Block - Fourth floor Pour - 1 completed, Pour - 2 in progress.
B- Block - Eleventh floor Pour -1 completed, Pour - 2 in progress.
C- Block - Thirteenth floor Pour -1 completed, Pour -2 in progress.
D- Block - Sixth floor completed.
Clubhouse - Second floor level slab shuttering in progress.

1st February 2022 Report

1st January 2022 Report

A- Block - Second floor Roof slab concrete in progress.
B- Block - Tenth floor shuttering in progress.
C- Block - Eleventh floor Reinforcement in progress.
D- Block - Third floor Roof slab concrete in progress.
Clubhouse - Ground floor roof slab concrete in progress.

1st January 2022 Report

1st December 2021 Report

A- Block - Third floor level Reinforcement & Shuttering in progress.
B- Block - Seventh floor wall Reinforcement & Shuttering in progress.
C- Block - Eighth floor wall Reinforcement & Shuttering in progress.
D- Block - Third floor Level ready for casting.
Clubhouse - Ground floor to First floor columns & walls casting in progress.

1st December 2021 Report

1st November 2021 Report

Second floor level Reinforcement & Shuttering in progress.
B- Block - Fourth floor to Fifth floor Reinforcement & Shuttering in progress.
C- Block - Sixth floor Reinforcement & Shuttering in progress.
D- Block - Third floor Level Shuttering in progress.
Clubhouse - Ground floor Reinforcement & shuttering in progress.

1st October 2021 Report

1st October 2021 Report

A- Block - Ground floor to First floor Reinforcement in progress.
B- Block - Second floor roof slab shuttering & Reinforcement in progress.
C- Block - Third floor Roof slab shuttering & Reinforcement in progress.
D- Block - First floor roof slab in progress.
Non Tower Area (East A&B -Block) - Podium slab completed.
Non Tower Area (West C&D -Block) - Podium slab completed.
Clubhouse - Ground floor slab shuttering in progress.

1st October 2021 Report

1st September 2021 Report

A- Block : Ground floor to First floor shuttering in progress.
B- Block : Second floor to Third floor wall shuttering in progress.
C- Block : Second Floor to Third Floor wall shuttering in progress.
D- Block : First floor to Second floor wall shuttering in progress.
Non Tower Area (East A&B -Block) : Podium slab concrete work in progress.
Non Tower Area (East A&B -Block) : Podium slab concrete work in progress.
Clubhouse : 1st Basement to Ground floor level column and Tanks Shuttering and Concrete work in progress.

1st September 2021 Report

1st August 2021 Report

A- Block: Ground floor to First floor shuttering in progress.
B- Block: Second floor slab shuttering & Reinforcement in progress.
C- Block: 2nd Floor to 3rd Floor wall Reinforcement & shuttering in progress.
D- Block: Ground floor to First floor wall shuttering & Reinforcement in progress.
Non Tower Area (East A&B-Block): Podium slab level shuttering in progress.
Non Tower Area (West C&D-Block): South west podium slab completed, North west Podium slab shuttering in progress.
Clubhouse: 1st Basement to Ground floor level column Reinforcement & Shuttering in progress.

1st August 2021 Report

1st July 2021 Report

A-Block : Ground floor to First floor Reinforcement in progress.
B-Block : First floor to Second floor Reinforcement & shuttering in progress.
C-Block : Second floor level shuttering in progress.
D-Block : Ground floor to First floor Reinforcement in progress.
Non Tower Area (East A&B -Block) : South east Podium slab shuttering in progress, North east retaining wall in progress.
Non Tower Area (West C&D -Block) : South west podium slab completed, North west Retaining wall in progress.
Club house : B2 Level to B1 Columns & Retaining wall Reinforcement & shuttering in progress.

1st July 2021 Report

1st June 2021 Report

A- Block: Ground floor to First floor Reinforcement in progress.
B- Block: Ground floor to First floor Reinforcement completed, shuttering in progress.
C- Block: First floor to Second floor Reinforcement in progress.
D- Block: Ground floor Reinforcement & Shuttering in progress.
Non Tower Area (East A&B -Block): 1st Basement to Podium slab Reinforcement in progress.
Non Tower Area (West C&D -Block): 1st Basement to Podium slab Reinforcement in progress.
Club house: 2nd Basement shuttering in progress.

1st June 2021 Report

1st May 2021 Report

A- Block : Ground floor to First floor Reinforcement in progress.
B- Block : Ground floor to First floor Reinforcement in progress.
C- Block : First floor level slab shuttering in progress.
D- Block : Ground floor shuttering & Reinforcement in progress.

1st May 2021 Report

1st April 2021 Report

A- Block : Ground floor slab Reinforcement in progress.
B- Block : Ground floor slab Reinforcement in progress.
C- Block : Ground floor to First floor walls Reinforcement and shuttering in progress.
D- Block : 1st Basement to Ground floor column and shuttering walls concrete in progress.

1st April 2021 Report

1st March 2021 Report

A-Block : Ground Floor slab shuttering in progress.
B-Block : Ground Floor slab shuttering in progress.
C-Block : Ground Floor transfer slab Reinforcement in progress.
D-Block : 2nd Basement level to 1st Basement level column casting in progress.

1st March 2021 Report

1st February 2021 Report

A-Block : 1st basement slab Reinforcement in progress.
B-Block : 1st basement shuttering in progress.
C- Block : Podium shuttering in progress.
D- Block : 2nd basement Reinforcement in progress.

* Work in progress with adequate work force even in pandemic situation.

1st February 2021 Report

1st January 2021 Report

A-Block : Basement 2 slab work in progress.
B-Block : Basement 2 slab work in progress.
C-Block : Basement 1 columns shuttering work in progress.
D-Block : Basement 3 columns shuttering work in progress.

* Work in progress with adequate work force even in pandemic situation.

1st January 2021 Report

1st December 2020 Report

A-Block: Basement -2 Slab work in progress.
B-Block: Basement -2 Slab work in progress.
C- Block: Basement-1 Shuttering Work in Progress.
D-Block: Raft Concrete work in progress.

* Work in progress with adequate work force even in pandemic situation.

1st December 2020 Report

1st November 2020 Report

A-Block: Basement -2 slab & beam shuttering work in progress.
B-Block: Basement -2 Floor slab & beam shuttering work in progress.
C- Block: Basement-2 Floor slab completed. And basement-2 to basement-1 wall reinforcement work in progress.
D-Block: Raft reinforcement in progress.

* Work in progress with adequate work force even in pandemic situation.

1st November 2020 Report

1st October 2020 Report

A- Block Raft concreting is in progress
B- Block Raft Concrete completed, walls reinforcement in
C- Block basement 2nd floor slab shutteering in progress
D- Block Raft Reinforcement work in Progress

* Work in progress with adequate work force even in pandemic situation.

1st October 2020 Report

1st September 2020 Report

A- Block Raft Reinforcement in Progress
B- Block Raft Reinforcement in Progress
C- Block Basement 3 & 2 Level Column concrete in Progress
D- Block Raft PCC completed

* Work in progress with adequate work force even in pandemic situation.

1st September 2020 Report

1st August 2020 Report

A and B block Tower foundation reinforcement progress
C Block Raft foundation completed and C block Tower basement column reinforcement progress.

* Work in progress with adequate work force even in pandemic situation.

1st August 2020 Report

19th June 2020 Report

19th June 2020 Report

18th May 2020 Report

Sentring Work Completed for 3 Basements.

18th May 2020 Report

18th February 2020 Report

Excavation For 3 Basements Completed.

18th February 2020 Report