1st September 2022 Report
A- BLOCK - 20th Floor Pour- 1 completed, Pour-2 slab Reinforcement in progress.
B- BLOCK - 27th Floor wall shuttering in progress.
C- BLOCK - G+27th Floors completed.
D- BLOCK - 22nd Floor Pour- 1 completed, Pour- 2 shuttering in progress.
Clubhouse - 5th Floor slab Reinforcement in progress.
1st September 2022 Report
1st September 2021 Report
A- Block : Ground floor to First floor shuttering in progress.
B- Block : Second floor to Third floor wall shuttering in progress.
C- Block : Second Floor to Third Floor wall shuttering in progress.
D- Block : First floor to Second floor wall shuttering in progress.
Non Tower Area (East A&B -Block) : Podium slab concrete work in progress.
Non Tower Area (East A&B -Block) : Podium slab concrete work in progress.
Clubhouse : 1st Basement to Ground floor level column and Tanks Shuttering and Concrete work in progress.
1st September 2021 Report
1st September 2020 Report
A- Block Raft Reinforcement in Progress
B- Block Raft Reinforcement in Progress
C- Block Basement 3 & 2 Level Column concrete in Progress
D- Block Raft PCC completed
* Work in progress with adequate work force even in pandemic situation.
1st September 2020 Report
18th February 2020 Report
Excavation For 3 Basements Completed.
18th February 2020 Report